National Highway 230 (NH 230), also known as Kisan Path and Lucknow outer ring road is a National Highway in India. Lucknow outer ring road is an 8 lane (4 each side)104 km long road project.

  • Mar 2019: 15 km of the road project was completed and inaugurated.
  • May 2020: Work on rest of road project progressing. [2]
  • Oct 2020: Outer ring road to be ready by December 2021.[3]
  • Oct 2021: work on remaining 76 kms of outer ring road is progressing and is expected to be completed by June 2022.
  • Feb 2022: After six months the ring road is ready, the work is going on very fast. Earthworks from Agra Expressway to Hardoi Road have almost been completed.

DECG Scope –

DECG International supplied a large number of Strip Seal Expansion Joints.

Key Data –

 

Products:

Strip Seal Expansion Joints

Installed:

2020

City:

Lucknow